Day 78 - June 12, 2003 - Gas line


Back to kitchen page ......Previous construction day ......Next construction day

Johnny drills a hole for the new silcock. This is a frostfree type that does not have to be drained for the winter.


Preparing the silcock.


Sal starts putting the gas pipe together.


Gas pipe outside work is complete.


Putting together the inside piping.


Inside piping complete - note connection to yellow flexible pipe for the run across the basement.


Outside pipe after painting all pipes - note the pressure test guage. Pressure test will be repeated for gas inspector tomorrow. Then gas company will hook up meter.


Sal applies some muscle in connecting basement run to the run from the cooktop through the crawl space.


Finished silcock.


Silcock piping tied into existing plumbing after shut-off, where the old silcock pipe was cut.